How long until Morrison has a grocery store you can walk to? On October 6 the town board gave that question a developer, a list of anchor tenants and a contract. It did not give it a date, because the agreement ties its schedule to the land transfer and to the town's sewer capacity.
The site is about 16 acres along C-470, just north of the Morrison Road interchange. Until the end of the 2023 season it was part of Bandimere Speedway. Two steps on the town's side decide when anything gets built there. The first is a plat approval for the land next door. The second is the expansion of Morrison's own wastewater plant.
What the board actually signed
The trustees voted 5–1 to name Red Rocks Gateway LLC as the town's preferred developer for the parcel, the Denver Post reported. The group is led by Nick Larson of Boulder-based Bear Peak Development. His partners are Jeremy Fey, Tyler Fey, Bryan Levitt of Nava Real Estate and Craig Campbell of Starwood Land. At the same meeting the board turned down a $5.5 million offer from Bear Creek Development Corporation. That's the Morrison company that owns the 47 acres next to the town's future parcel. Trustee John Leonard voted no because he wanted more time to review both proposals.
The pre-development agreement in the October 6 board packet calls for an anchor grocery use, an anchor lodging use, and a mix of boutique, local and regional shops. The project has to be commercial. Housing is not allowed. Larson told the Denver Post the town has asked for a hotel, a grocery store, and a music and event venue that "complements, not competes" with Red Rocks. Trustee Angela Bernhardt, who made the motion, told the paper the town wants "something that brings business in the winter."
The agreement also says plainly that it approves nothing on the ground. No zoning, site plan or building permit comes with it, and it creates no vested rights. It sets up a working relationship, and every approval still lies ahead.
The clock is paused until the town owns the land
Morrison doesn't own the 16 acres yet. Back in 2024, Copart, the auto auction company that bought the speedway property, agreed to hand the parcel to the town in exchange for annexation. The agreement says the land is expected to transfer once Copart's final plat for its own parcel is approved.
That plat sits at the top of the whole schedule. The contract runs until November 1, 2027. Its term, the developer's due diligence period and every deadline in it are paused and extended day for day for as long as the town doesn't hold title. Even getting onto the site for soil and traffic studies takes a separate access agreement with Copart, since Copart still owns the ground.
Under the 2024 annexation terms, the rest of the old speedway becomes a Copart vehicle center. Plans call for about 66 acres of outdoor vehicle storage, weekday hours and about 20 employees. Copart's counsel said there would be no live auctions and no crushing or stacking of vehicles, and the deal limits the site to three water taps. Moving that site plan forward is what eventually turns the 16 acres into town property.
What the developer owes, once the clock starts
After the town holds title, the milestones follow a set order:
- Due diligence, 270 days. During this period the developer decides whether the project is feasible, and the agreement lets it run environmental, geotechnical, traffic, water, sewer, drainage and market studies on the parcel.
- Interest from a grocer and a lodging operator, within nine months. The developer has to make diligent efforts to get an expression of interest from a grocery or specialty grocery operator and from a lodging user. Missing that target is not a default as long as the effort continues in good faith.
- A conceptual development plan, within 12 months. It must include a timeline, proposed uses, building design, streets, trails, parking, a phasing plan, water and sewer demand, renderings, and a pedestrian connection to downtown Morrison.
- At least two public presentations. Afterward, the Board of Trustees sends written recommendations, and the developer has to address them in the final plan.
Those public presentations are the first time residents will see renderings, a street layout or the planned walking route to Bear Creek Avenue. The contract also tells the developer to favor tenants that are "boutique, high-quality, destination-oriented, Colorado based, independent, and artisan," along with enough national and regional names to support financing.
The sewer plant may set the real timeline
The town is reserving sewer capacity equal to 200 homes' worth of use for the project. But no sewer tap on the property can go into service until the town's expanded wastewater treatment plant is finished. The town is holding the same amount of water capacity, 200 taps' worth, which stands in for the usual will-serve letter.
So no shop on the parcel can use sewer until the plant expansion is done. Morrison's plant is rated for 0.35 million gallons per day, and the expansion is designed to take it to 0.6. That would add about 1,250 homes' worth of capacity, so the gateway's 200 is a fraction of what's being built. In December 2025 the town's fee analysis estimated the base cost at $25.5 million.
The amended 2026–2030 utility capital plan spreads $16.8 million for the plant across five years:
| Year | Wastewater plant allocation |
|---|---|
| 2026 | $1,000,000 |
| 2027 | $7,000,000 |
| 2028 | $7,000,000 |
| 2029 | $1,000,000 |
| 2030 | $800,000 |
| Total | $16,800,000 |
Most of the money is scheduled for 2027 and 2028. The 2027 budget packet lists "Wastewater Treatment Plant Expansion" among next year's utility capital projects. Because sewer service on the parcel waits for that expansion, when the plant comes online will help decide when a finished grocery store could open.
The financing question comes later
Larson told the board the financing plan could take time and might include an urban renewal authority, the Canyon Courier reported. The contract places that decision after a financing plan is complete. At that point the two sides decide together whether a URA is reasonably necessary. If they decide it is, the developer pays for the blight study and urban renewal plan, and the board considers them under the Colorado Urban Renewal Law, with no obligation to adopt either. The same section lets the town look at putting tax revenue the project itself generates, including town property, sales and lodging taxes, toward the financing. Any URA would come up as a separate public decision before the board.
What's on Morrison's calendar now
The next public step comes before anything with the developer. The Board of Trustees holds its second hearing on the 2027 budget and Capital Improvement Plan on Tuesday, November 17, at 6 p.m. at Town Hall. That's the plan that funds the wastewater expansion. It's the clearest view residents will get this year of the infrastructure the gateway project depends on.
Downtown, meanwhile, Kiki's Health Cafe has set November as its target to open at 300 Bear Creek Avenue, in a building first designed as Morrison's post office. The Canyon Courier reported that it's the second location of the Evergreen cafe, run by Tiffani and Rand Packer, who also own La Rocca Rossa across the street. The plans include a drive-through, a full coffee bar, grab-and-go bowls, breakfast burritos and gelato. Whatever happens at the gateway, the east-side parcel is meant to link back to Bear Creek Avenue by a pedestrian connection that's already written into the development plan requirements.
If you live in Morrison and want to talk through how the gateway project, the wastewater expansion or the town's budget hearings might affect your plans, I'm happy to walk through it with you. Laura Gilsdorf is here when you're ready. Let's Connect.